Operation Manual of WEICHAI GENSET
ventilated room with room temperature
of 5~25 ℃ , away from direct sunlight,
heat sources, liquids and harmful
substances, and it shall not be placed
upside down, impacted or stressed.
If the battery is not used for a long time,
it will slowly discharge until it is scrapped.
Therefore, to ensure that the battery is
always in good working condition, it shall
be charged at regular intervals.
The recommended charging interval is:
6 months at storage temperature less
than or equal to 20℃;
3 months at storage temperature of
20~30℃.
Installation requirements for set
The following matters shall be
determined before the set is installed:
1. Total usable area and limitations.
The machine room shall have enough
space to accommodate the following
equipment: generator set, related
control cabinets (such as remote control
cabinets, parallel cabinets, automatic
switching cabinets, etc.) of generator set,
air inlet and ventilation systems, smoke
exhaust systems (exhaust pipes,
silencers, etc.).
2. Any limitation to noise, and
requirements on noise in operating
environment such as office or residential
area.
3. The feasibility of machine room
passage, set transportation and
installation shall meet the requirements
on the space for set operation,
installation, service and maintenance.
4. Accessibility of service vehicle
Foundation
The generator set does not need a
specific foundation. The set can be
directly installed on horizontal concrete
ground with sufficient strength. It is
recommended to add a proper floor mat
between the base frame and the ground,
because the floor mat can not only make
up for the slight unevenness on the
ground, but also increase the resistance
between the set and the ground and
improve the shock absorption function.
The ground must be able to bear the
static weight of the generator set.
1 Concrete foundation
The concrete foundation shall have a
period of not less than seven days from
the beginning of pouring to the
installation of the set for drying and
solidification. The foundation level shall
be controlled within a ±0.5°plane, and
the foundation shall be built on a
compacted hard ground. The concrete
thickness is selected according to the set
power. For generator sets of 120kW and
below, the concrete thickness is 100mm
or above. For generator sets of 150kW-
1000kW, the concrete thickness is
200mm. Although this data is applicable
to most foundations, it is recommended
to determine the foundation bearing
capacity after consulting local
regulations and foundation analysis
reports of buildings.
2 Connection
Fuel, water and exhaust pipes transmit
vibration for long distances. All piping
and electrical connections shall have
flexible connections as a transition to
prevent damage to the set or ancillary
equipment caused by set vibration.
7