Appendix 2 I/O Timing Sequence Figure of F2000 Series Numerical Control System
Level 3 perforation timing sequence with
M07
M08
THC
Torch
up
time
Ignition
High Preheat
Low Preheat
THC Enable
TorchUp
Pierce 1
Pierce 2
Pierce 3
Blow
Cutting
Note: Red words
mean output
port. Bold
black words
mean parameter.
Appendix fig 2.2 Flame cutting timing sequence (Level 3 perforation with THC)
M07
Level 1 perforation timing sequence with
M08
no THC
Torch
up
time
Ignition
Low Preheat
TorchDn
TorchUp
Pierce 3
Blow
Cutting
Note: Red words
mean output
port. Bold
black words
mean parameter.
Appendix fig 2.3 Flame cutting timing sequence (Level 1 perforation with no THC)